West Coast Expressway to complete four stretches by end of 2023

By BERNAMA | 12 July 2023


IPOH: West Coast Expressway Sdn Bhd (WCESB) is aiming to complete four more sections of the West Coast Expressway — the SKVE, Banting, Assam Jawa and South Taiping sections — by the end of this year.

WCE highway operations manager Syed Muhd Naguib Syed Mohd said the 35-kilometre (km) Section 11, Beruas-South Taiping section was 88% complete and is expected to begin operations early year.

"Construction now involves elements of engineering, toll, slope and mechanical work,” he said here on Monday.

Syed Muhd Naguib said as the route passes through Bubu Forest Reserve, WCE will also build an animal box culvert as an environmental conservation measure.

2023-07-12 07_43_10-Windows Sandbox


In addition, for the Perak route, WCE plans to build four Rest and Service Areas (R&R) - Teluk Intan R&R (north and south), Sungai Wangi R&R (south), Ayer Tawar R&R (north) and Sg Nyior R&R (north and south), he said, adding that it would also have two electric vehicle charging facilities at Lekir and Teluk Intan.

He also said that the number of vehicles using the WCE has increased by 30%, to 50,000 to 60,000 vehicles daily.

"During the recent Aidilfitri celebrations, traffic volume reached 100,000 vehicles a day and 85,000 for Raya Aidiladha,” he said.

WCE had previously stated that the 233km expressway would be completed by 2025.